Change Orders #1 to Rohde Brothers, Inc. contract as part of the AWWTP Sludge Piping and Digester Heat Exchanger Replacement Project totaling $9,730 resulting in a decrease in contingency from $241,800 to $ 232,070.

Presentation Filed Introduced July 18, 2024

What this record is

Held by
Rohde Brothers, Inc 9 records across this site
Amount
$242K
Runs until
no end date published in this record
Type
amendment
Field
Utilities & energy

Read automatically from the title of the official record. The source document below is authoritative.

Rohde Brothers, Inc also holds

Change orders #7, #8, and #9 to Rohde Brothers, Inc. contract as part of the AWWTP Sludge Piping and Digester Heat Exchanger Replacement Project total… $31K Appleton, WI Request to award the Anaerobic Digester Inspection, Maintenance, & Improvements Construction project base bid plus Alternatives 1 and 5 to Rohde Broth… $1.70M Appleton, WI Approve Change Order #6 to Rohde Brothers, Inc. contract as part of the AWWTP Sludge Piping and Digester Heat Exchanger Replacement Project totaling $… $134K Appleton, WI Change Order #4 to Rohde Brothers, Inc. contract as part of the AWWTP Sludge Piping and Digester Heat Exchanger Replacement Project totaling $31,269 r… $181K Appleton, WI Change Orders #2 and #3 to Rohde Brothers, Inc. contract as part of the AWWTP Sludge Piping and Digester Heat Exchanger Replacement Project totaling $… $232K Appleton, WI

All 9 records for Rohde Brothers, Inc →

Committee
Finance Committee
Introduced
July 18, 2024
On agenda
July 22, 2024
Passed
July 22, 2024

Where it was heard