Request to award the Anaerobic Digester Inspection, Maintenance, & Improvements Construction project base bid plus Alternatives 1 and 5 to Rohde Brothers Inc., in the amount of $1,547,320 with a 10% contingency of $154,732 for a project total not to exceed $1,702,052 along with the following 2025-2026 Budget carryover appropriations (2/3 vote of Council required): Wastewater Utility Fund 2025 Digester Cathodic Protection & Corrosion Control - $774,925 2025 Equipment Repairs & Maintenance - $927,127 2026 Digester Cathodic Protection & Corrosion Control + $774,925 2026 Equipment Repairs & Maintenance + $927,127

Report Action Item Passed Introduced March 5, 2026

What this record is

Held by
Rohde Brothers Inc 9 records across this site
Amount
$1.70M
Runs until
Not stated in the agenda text — the term is normally in the signed agreement, attached to the original item ↗
Type
award
Field
Construction
Compared to
$181K – $888K the middle half of 9 other Rohde Brothers Inc contracts; median $232K

construction contracts in WI that end within a year →
Governments publish the end date in the award. That date is when the work goes back out to bid, and it is usually stated years ahead.

Read automatically from the title of the official record. The source document below is authoritative.

Rohde Brothers Inc also holds

Change orders #7, #8, and #9 to Rohde Brothers, Inc. contract as part of the AWWTP Sludge Piping and Digester Heat Exchanger Replacement Project total… $31K Appleton, WI Approve Change Order #6 to Rohde Brothers, Inc. contract as part of the AWWTP Sludge Piping and Digester Heat Exchanger Replacement Project totaling $… $134K Appleton, WI Change Order #4 to Rohde Brothers, Inc. contract as part of the AWWTP Sludge Piping and Digester Heat Exchanger Replacement Project totaling $31,269 r… $181K Appleton, WI Change Orders #2 and #3 to Rohde Brothers, Inc. contract as part of the AWWTP Sludge Piping and Digester Heat Exchanger Replacement Project totaling $… $232K Appleton, WI Request to award Appleton Water Treatment Facility Carbon Dioxide System Rehabilitation Project Base Bid to Rohde Brothers, Inc., in the amount of $20… $229K Appleton, WI

All 9 records for Rohde Brothers Inc →

Committee
Finance Committee
Introduced
March 5, 2026
On agenda
March 9, 2026
Passed
March 18, 2026

Where it was heard

Common Council Mar 18, 2026 approved Pass Finance Committee Mar 9, 2026 recommended for approval Pass

Watch what Appleton buys

This is one award. Appleton signs them continuously, and each one names a company and a date it runs out. Say what you sell and we will email you when the next one matches.

Free for 14 days, no card — and nothing charges itself: at day 14 the emails simply stop unless you choose to subscribe ($19 a month). One email when something matches, and nothing else. Unsubscribe from any of them. Searching stays free — it is public record.

↑ Back to top