24-1513
Change Orders #2 and #3 to Rohde Brothers, Inc. contract as part of the AWWTP Sludge Piping and Digester Heat Exchanger Replacement Project totaling $50,701 resulting in a decrease in contingency from $232,070 to $181,369.
What this record is
- Held by
- Rohde Brothers, Inc 9 records across this site
- Amount
- $232K
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Utilities & energy
Read automatically from the title of the official record. The source document below is authoritative.
Rohde Brothers, Inc also holds
Change orders #7, #8, and #9 to Rohde Brothers, Inc. contract as part of the AWWTP Sludge Piping and Digester Heat Exchanger Replacement Project total… Request to award the Anaerobic Digester Inspection, Maintenance, & Improvements Construction project base bid plus Alternatives 1 and 5 to Rohde Broth… Approve Change Order #6 to Rohde Brothers, Inc. contract as part of the AWWTP Sludge Piping and Digester Heat Exchanger Replacement Project totaling $… Change Order #4 to Rohde Brothers, Inc. contract as part of the AWWTP Sludge Piping and Digester Heat Exchanger Replacement Project totaling $31,269 r… Request to award Appleton Water Treatment Facility Carbon Dioxide System Rehabilitation Project Base Bid to Rohde Brothers, Inc., in the amount of $20…All 9 records for Rohde Brothers, Inc →
- Committee
- Finance Committee
- Introduced
- November 21, 2024
- On agenda
- November 25, 2024
- Passed
- December 4, 2024