Change Orders #2 and #3 to Rohde Brothers, Inc. contract as part of the AWWTP Sludge Piping and Digester Heat Exchanger Replacement Project totaling $50,701 resulting in a decrease in contingency from $232,070 to $181,369.

Presentation Filed Introduced November 21, 2024

What this record is

Held by
Rohde Brothers, Inc 9 records across this site
Amount
$232K
Runs until
no end date published in this record
Type
amendment
Field
Utilities & energy

Read automatically from the title of the official record. The source document below is authoritative.

Rohde Brothers, Inc also holds

Change orders #7, #8, and #9 to Rohde Brothers, Inc. contract as part of the AWWTP Sludge Piping and Digester Heat Exchanger Replacement Project total… $31K Appleton, WI Request to award the Anaerobic Digester Inspection, Maintenance, & Improvements Construction project base bid plus Alternatives 1 and 5 to Rohde Broth… $1.70M Appleton, WI Approve Change Order #6 to Rohde Brothers, Inc. contract as part of the AWWTP Sludge Piping and Digester Heat Exchanger Replacement Project totaling $… $134K Appleton, WI Change Order #4 to Rohde Brothers, Inc. contract as part of the AWWTP Sludge Piping and Digester Heat Exchanger Replacement Project totaling $31,269 r… $181K Appleton, WI Request to award Appleton Water Treatment Facility Carbon Dioxide System Rehabilitation Project Base Bid to Rohde Brothers, Inc., in the amount of $20… $229K Appleton, WI

All 9 records for Rohde Brothers, Inc →

Committee
Finance Committee
Introduced
November 21, 2024
On agenda
November 25, 2024
Passed
December 4, 2024

Where it was heard

Finance Committee Dec 4, 2024 received and filed Finance Committee Nov 25, 2024