docketcity.com
26-0777

Change orders #7, #8, and #9 to Rohde Brothers, Inc. contract as part of the AWWTP Sludge Piping and Digester Heat Exchanger Replacement Project totaling -$8,001 resulting in an increase in contingency from $23,110 to $31,111.

Report Action Item Action Item Introduced June 4, 2026

What this record is

Held by
Rohde Brothers, Inc 9 records across this site
Amount
$31K
Runs until
no end date published in this record
Type
amendment
Field
Utilities & energy

Read automatically from the title of the official record. The source document below is authoritative.

Rohde Brothers, Inc also holds

Request to award the Anaerobic Digester Inspection, Maintenance, & Improvements Construction project base bid plus Alternatives 1 and 5 to Rohde Broth… $1.70M Appleton, WI Approve Change Order #6 to Rohde Brothers, Inc. contract as part of the AWWTP Sludge Piping and Digester Heat Exchanger Replacement Project totaling $… $134K Appleton, WI Change Order #4 to Rohde Brothers, Inc. contract as part of the AWWTP Sludge Piping and Digester Heat Exchanger Replacement Project totaling $31,269 r… $181K Appleton, WI Change Orders #2 and #3 to Rohde Brothers, Inc. contract as part of the AWWTP Sludge Piping and Digester Heat Exchanger Replacement Project totaling $… $232K Appleton, WI Request to award Appleton Water Treatment Facility Carbon Dioxide System Rehabilitation Project Base Bid to Rohde Brothers, Inc., in the amount of $20… $229K Appleton, WI

All 9 records for Rohde Brothers, Inc →

Committee
Finance Committee
Introduced
June 4, 2026
On agenda
June 8, 2026
Passed
June 8, 2026

Where it was heard

Finance Committee Jun 8, 2026