- 8 Request to approve the following 2025 Budget amendment: CEA Capital Projects Federal Grants +$134,180 Vehicles +$134,180 To record EECGB grant award and associated expense (2/3 vote of council required).
- 9 Request to approve Relocation Order for the Parcel of Land with Tax Key No.31-3-0316-03
- 10 Request to approve contract to Conventions, Sports & Leisure International (CSL) for consulting services for a contract not-to-exceed $79,500.
- 11 Request to approve authorization to open dedicated bank account for Cryptocurrency seizure returns.
- 12 Request to award Unit DE-25 Miscellaneous Sidewalk & Concrete Street Excavation Repairs to Al Dix Inc in an amount not to exceed $1,008,850.
- 13 Request to award Unit W-25 Sewer & Water Reconstruction-Bell, Brewster, Alexander, Melrose to Kruczek Construction Inc. in the amount of $2,312,222.22 with a 3% contingency of $70,000 for a project total not to exceed $2,382,222.22.
- 14 Request to award Unit U-25 Sewer & Water Reconstruction-Lawe, Durkee, Bellaire to Kruczek Construction Inc. in the amount of $2,525,555.55 with a 2.8% contingency of $70,000 for a project total not to exceed $2,595,555.55.
- 15 Request to award Unit X-25 Water Reconstruction-Calumet St to Calnin & Goss LLC in the amount of $1,138,754.30 with a 3% contingency of $35,000 for a project total not to exceed $1,173,754.30.
- 16 Request to award Unit A-25 Concrete Paving to Vinton Construction Company in the amount of $4,187,819.61 with a 1.5% contingency of $65,000 for a project total not to exceed $4,252,819.61.
- 17 Request to approve the following 2025 Budget amendment: CD - New & Redevelopment Projects Miscellaneous Revenue +$100,000 Consulting Services +$100,000 To record cost reimbursement agreement with Thrivent Financial (2/3 vote council required).
- 7. Information Items
- 19 Contract 88-24 was awarded to Green Bay Pipe & TV for $250,000 for Sewer Cleaning and Televising. Payments issued to date total $228,716.62. Request final payment of $15,426.64.
- 20 Contract 4-23 was awarded to Great Lakes Mechanical for $232,000 with a contingency of $27,840 for H&J Bldg HVAC Design. Change orders were approved totaling $6,763.70. Final contract amount is $238,763.70 with a contingency of $21,076.30. Payments issued to date total $226,825.52. Request final payment of $11,938.18.
- 21 Contract 116-22 was awarded to Rohde Brothers for $333,450 with a contingency of $40,014 for WW Bio-Gas & Boiler. Change orders were approved totaling $37,625. Final contract amount is $371,075 with a contingency of $2,389. Payments issued to date total $355,726.80. Request final payment of $15,348.20.
- 22 Contract 103-23 was awarded to Restoration Systems, Inc. for $689,825 with a contingency of $10,175 for DD-23 Parking Ramp Repairs and Maintenance. Payments issued to date total $667,186.65. Request final payment of $22,637.35.
- 23 Contract 30-24 was awarded to Advance Construction Inc. for $980,663 with a contingency of $10,000 for Z-24 Water Reconstruction No. 3. Payments issued to date total $404,554.52. Request final payment of $474,764.73.
- 8. Adjournment
Watch Appleton
This is one agenda. Appleton publishes another every few weeks, and the thing you care about is rarely on the one you happened to find. Name it and we will email you when it appears.
Free for 14 days, no card — and nothing charges itself: at day 14 the emails simply stop unless you choose to subscribe ($19 a month). One email when something matches, and nothing else. Unsubscribe from any of them. Searching stays free — it is public record.