Contract 116-22 was awarded to Rohde Brothers for $333,450 with a contingency of $40,014 for WW Bio-Gas & Boiler. Change orders were approved totaling $37,625. Final contract amount is $371,075 with a contingency of $2,389. Payments issued to date total $355,726.80. Request final payment of $15,348.20.