25-0083
Contract 116-22 was awarded to Rohde Brothers for $333,450 with a contingency of $40,014 for WW Bio-Gas & Boiler. Change orders were approved totaling $37,625. Final contract amount is $371,075 with a contingency of $2,389. Payments issued to date total $355,726.80. Request final payment of $15,348.20.
What this record is
- Amount
- $371K
- Runs until
- no end date published in this record
- Type
- award
Read automatically from the title of the official record. The source document below is authoritative.
- Committee
- Finance Committee
- Introduced
- February 6, 2025
- On agenda
- February 10, 2025
- Passed
- February 10, 2025