Contract 4-23 was awarded to Great Lakes Mechanical for $232,000 with a contingency of $27,840 for H&J Bldg HVAC Design. Change orders were approved totaling $6,763.70. Final contract amount is $238,763.70 with a contingency of $21,076.30. Payments issued to date total $226,825.52. Request final payment of $11,938.18.