docketcity.com
25-0082

Contract 4-23 was awarded to Great Lakes Mechanical for $232,000 with a contingency of $27,840 for H&J Bldg HVAC Design. Change orders were approved totaling $6,763.70. Final contract amount is $238,763.70 with a contingency of $21,076.30. Payments issued to date total $226,825.52. Request final payment of $11,938.18.

Presentation Filed Introduced February 6, 2025

What this record is

Held by
Great Lakes Mechanical
Amount
$239K
Runs until
Not stated in the agenda text — the term is normally in the signed agreement, attached to the original item ↗
Type
award
Field
Construction

construction contracts in WI that end within a year →
Governments publish the end date in the award. That date is when the work goes back out to bid, and it is usually stated years ahead.

Read automatically from the title of the official record. The source document below is authoritative.

Committee
Finance Committee
Introduced
February 6, 2025
On agenda
February 10, 2025
Passed
February 10, 2025

Where it was heard

Finance Committee Feb 10, 2025 received and filed

Watch what Appleton buys

This is one award. Appleton signs them continuously, and each one names a company and a date it runs out. Say what you sell and we will email you when the next one matches.

Free for 14 days, no card — and nothing charges itself: at day 14 the emails simply stop unless you choose to subscribe ($19 a month). One email when something matches, and nothing else. Unsubscribe from any of them. Searching stays free — it is public record.

↑ Back to top