docketcity.com

Finance Committee

February 9, 2026 ·5:30 PM Final

Council Chambers, 6th Floor

Agenda — 22 items

  1. 1. Call meeting to order
  2. 2. Pledge of Allegiance
  3. 3. Roll call of membership
  4. 4. Approval of minutes from previous meeting
  5. 5 January 26, 2026 Meeting Minutes 26-0152 approved Pass
  6. 5. Public Hearing/Appearances
  7. 6. Action Items
  8. 8 Request to award sole source contract for Parks and Recreation Building Furniture Upgrades to Nordon Business Environments in the amount of $91,681.14, with a 5% contingency of $4,584.06 for a total project not to exceed $96,265.20. 26-0153 recommended for approval Pass
  9. 9 Request to award the design engineering contract for the 2026 Jaycee Park Court Design Project to McMahon in the amount of $35,120 with a 5% contingency of $1,756 for a total project not to exceed $36,876. 26-0174 recommended for approval Pass
  10. 10 Request to award Unit W-26 Sewer and Water Construction to Kruczek Construction in the amount of $2,585,585 with a 23% contingency of $60,000 for a project total not to exceed $2,645,585. 26-0159 recommended for approval Pass
  11. 11 Request to award Unit H-26 Northeast Sanitary Interceptor Sewer to PTS Contractors in the amount of $1,018,600 with a 20% contingency of $20,000 for a project total not to exceed $1,038,600. 26-0160 recommended for approval Pass
  12. 12 Request to award Unit DE-26 Miscellaneous Sidewalk and Concrete Street Repairs to Al Dix Concrete Inc. in the amount not to exceed $1,008,850. 26-0161 recommended for approval Pass
  13. 13 Request to award Unit A-26 Concrete Paving to Vinton Construction Company in the amount of $3,755,429.12 with a 15% contingency of $55,000 for a project total not to exceed $3,810,429.12. 26-0162 recommended for approval Pass
  14. 14 Request to approve Finance Committee Report for Preliminary Resolution 1-P-26 for Sanitary Laterals, Storm Laterals and Storm Main Construction. 26-0164 recommended for approval Pass
  15. 15 Request to approve Finance Committee Report for Preliminary Resolution 2-P-26 for Concrete Pavement, Driveway Aprons and Sidewalk Construction. 26-0163 recommended for approval Pass
  16. 16 Request to approve Development Agreement for Comet Ridge Development (North Appleton Properties, LLC). 26-0169 recommended for approval Pass
  17. 7. Information Items
  18. 18 Contract 59-25 was awarded to Vinton Construction Company for $1,370,111.56 with a contingency of $205,516.00 for WWTP Hardscape. Change orders were approved totaling $106,987.72. Final contract amount is $1,477,099.28 with a contingency of $98,528.28. Payments issued to date total $1,270,146.89. Request final payment of $206,952.39. 26-0151
  19. 19 Contract 21-24 was awarded to Peters Concrete Company for Unit H-23 Lightning Drive Extension Phase 1 for $1,544,853.12 with a contingency of $116,000. Three Change Orders have been approved in the amount of $265,960.36. Final contract amount is $1,810,813.48. Payments issued to date total $1,436,806.26. Request Final payment of $228,657.07. 26-0155
  20. 20 Contract 30-25 was awarded to Kruczek Construction for Unit U-25 Sewer & Water Reconstruction for $2,525,555.55 with a contingency of $70,000.00. Payments issued to date total $2,351,766.42. Request Final payment of $156,012.33. 26-0156
  21. 21 Contract 37-25 was awarded to Vinton Construction for Unit B-25 Asphalt Pavement Reconstruction for $1,285,258.51 with a contingency of $41,000.00. One Change Order was approved in the amount of $57,830.90. Final contract amount is $1,343,089.41. Payments issued to date total $1,211,671.86. Request Final payment of $131,417.42 26-0158
  22. 8. Adjournment adjourned Pass

Watch Appleton

This is one agenda. Appleton publishes another every few weeks, and the thing you care about is rarely on the one you happened to find. Name it and we will email you when it appears.

Free for 14 days, no card — and nothing charges itself: at day 14 the emails simply stop unless you choose to subscribe ($19 a month). One email when something matches, and nothing else. Unsubscribe from any of them. Searching stays free — it is public record.

↑ Back to top