docketcity.com
26-0162

Request to award Unit A-26 Concrete Paving to Vinton Construction Company in the amount of $3,755,429.12 with a 15% contingency of $55,000 for a project total not to exceed $3,810,429.12.

Report Action Item Passed Introduced February 5, 2026

What this record is

Held by
Vinton Construction Company 33 records across this site
Amount
$3.81M
Runs until
no end date published in this record
Type
award
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Vinton Construction Company also holds

Request to award the Appleton Wastewater Treatment Plant Truck Scale Paving Project contract to Vinton Construction Company in the amount of $384,566.… $423K Appleton, WI Report of Board of Public Works of 7/8/2026, of bids received for 10th Street (Chicago - Washington) Streetscape - Project WS-26-20; recommending awar… $120K Manitowoc, WI Report of Board of Public Works of 6/10/2026, of bids received for Silver Creek Stream Restoration, Project WS-26-19; recommending awarding to Vinton … $655K Manitowoc, WI Report of Board of Pubic Works of 3/4/2026, of bids received for 2026 Concrete Paving I Program, Project WS-26-1; recommending awarding to Vinton Cons… $1.91M Manitowoc, WI Report of Board of Public Works of 2/4/2026, of bids received for Red Arrow Beach Access Improvements, WS-26-14; recommending awarding to Vinton Const… $1.08M Manitowoc, WI

All 33 records for Vinton Construction Company →

Committee
Finance Committee
Introduced
February 5, 2026
On agenda
February 9, 2026
Passed
February 18, 2026

Where it was heard

Common Council Feb 18, 2026 approved Pass Finance Committee Feb 9, 2026 recommended for approval Pass