Contract 21-24 was awarded to Peters Concrete Company for Unit H-23 Lightning Drive Extension Phase 1 for $1,544,853.12 with a contingency of $116,000. Three Change Orders have been approved in the amount of $265,960.36. Final contract amount is $1,810,813.48. Payments issued to date total $1,436,806.26. Request Final payment of $228,657.07.