Contract 47-25 was awarded to Staab Construction Corp for $353,000 with a contingency of $8,825 for WWTP Removable Wall Storage. Change orders were approved totaling a credit of $9,054. Final contract amount is $343,946 with a contingency of $17,879. Payments issued to date total $317,280.47. Request final payment of $26,665.53.

Report Action Item Action Item Introduced January 21, 2026

What this record is

Held by
Staab Construction Corp 4 records across this site
Amount
$344K
Runs until
no end date published in this record
Type
award
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Staab Construction Corp also holds

Request to award Appleton Wastewater Treatment Plant M-K Tunnel Bridge Improvements Project contract to Staab Construction Corporation in the amount o… $131K Appleton, WI Contract 15-23 was awarded to Staab Construction Corporation for $5,063,000 with a contingency of $759,450 for the Belt Filter Press - Phase 1. Change… $5.30M Appleton, WI Award AWWTP Digester Cleaning and Inspection Support contract to Staab Construction Corporation in the amount of $122,600 with a 15% contingency of $1… $141K Appleton, WI
Committee
Finance Committee
Introduced
January 21, 2026
On agenda
January 26, 2026
Passed
January 26, 2026