Contract 15-23 was awarded to Staab Construction Corporation for $5,063,000 with a contingency of $759,450 for the Belt Filter Press - Phase 1. Change orders were approved totaling $238,855. Final contract amount is $5,301,855 with a contingency of $520,595. Payments issued to date total $5,270,917. Request final payment of $30,938.

Report Action Item Action Item Introduced July 31, 2025

What this record is

Held by
Staab Construction Corporation 4 records across this site
Amount
$5.30M
Runs until
no end date published in this record
Type
award
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Staab Construction Corporation also holds

Request to award Appleton Wastewater Treatment Plant M-K Tunnel Bridge Improvements Project contract to Staab Construction Corporation in the amount o… $131K Appleton, WI Contract 47-25 was awarded to Staab Construction Corp for $353,000 with a contingency of $8,825 for WWTP Removable Wall Storage. Change orders were ap… $344K Appleton, WI Award AWWTP Digester Cleaning and Inspection Support contract to Staab Construction Corporation in the amount of $122,600 with a 15% contingency of $1… $141K Appleton, WI
Committee
Finance Committee
Introduced
July 31, 2025
On agenda
August 4, 2025
Passed
August 11, 2025

Where it was heard