- 5 Finance Committee Meeting Minutes July 21, 2025
- 5. Public Hearing/Appearances
- 6. Action Items
- 8 Request to approve Riverside Cemetery Association reimbursement request for maintenance of Veteran graves
- 9 Request to approve the 2026 Special Assessment Policy
- 10 Request to approve sole source contract to Nordon Business Environments to purchase new workstations in the amount of $350,113
- 11 Request to award the Mead Pool Coating and ADA Upgrades Project contract to Cardinal Construction Co., Inc. in the amount of $424,727 with a 7% contingency of $29,731, for a project total not to exceed $454,458 along with the following budget amendment (2/3 vote of council required): Facilities Capital Projects Fund 2025 Parks Hardscapes - $144,878 Mead Pool Coating & ADA Upgrades + $144,878
- 12 Request to approve the following Budget amendment: Wastewater Utility Fund 2024 Aeration Process Upgrades - $19,845 Phosphorus Analyzer +$19,845 To fund the purchase of a Chemscan miniOP phosphorus analyzer (2/3 vote of Council required)
- 7. Information Items
- 14 Contract 36-22 was awarded to Van Ert Electric Co. for $1,595,000 with a contingency of $159,500 for the Substation Upgrade - Phase 5. Change orders were approved totaling $35,988.04. Final contract amount is $1,630,988.04 with a contingency of $123,511.96. Payments issued to date total $1,549,438.64. Request final payment of $81,549.40.
- 15 Contract 78-25 was awarded to Norcon Corporation for $144,842.94 with a contingency of $5,157.06 for Bridge Deck Sealing. Payments issued to date total $134,367.47. Request final payment of $7,071.97.
- 16 Contract 15-23 was awarded to Staab Construction Corporation for $5,063,000 with a contingency of $759,450 for the Belt Filter Press - Phase 1. Change orders were approved totaling $238,855. Final contract amount is $5,301,855 with a contingency of $520,595. Payments issued to date total $5,270,917. Request final payment of $30,938.
- 17 Change Order #1 to Contract 46-24 Unit G-24 Southpoint Commerce Park Sewer & Water and Grade & Gravel project with Carl Bowers & Sons Construction Co. totaling $55,000 resulting in a decrease in contingency from $65,000 to $10,000.
- 18 Appleton Water Treatment Facility Bulk Hypochlorite Tank Replacement Tank Purchase Awarded to GPI Corporation in the amount of $179,540.
- 19 Debt Issue Memo
- 20 2025 Mid Year Risk Report
- 8. Adjournment
Watch Appleton
This is one agenda. Appleton publishes another every few weeks, and the thing you care about is rarely on the one you happened to find. Name it and we will email you when it appears.
Free for 14 days, no card — and nothing charges itself: at day 14 the emails simply stop unless you choose to subscribe ($19 a month). One email when something matches, and nothing else. Unsubscribe from any of them. Searching stays free — it is public record.