Request to award the Appleton Wastewater Treatment Plant 2025 L-Building HVAC and Receiving Station Upgrades Project contract to August Winter & Sons, Inc. in the amount of $3,969,472 with a 12% contingency of $476,337 for a project total not to exceed $4,445,809 along with the following 2024 to 2025 budget carryover appropriation (2/3 vote of council required): 2024 Primary Clarifier Rebuild CIP - $895,487 2024 Blended Sludge Piping & Hex Rplcmnt CIP - $1,477,693 2024 L-Building HVAC Upgrades CIP - $2,072,629 2025 L-Building HVAC & Receiving Station Upgrades Proj +$4,445,809

Report Action Item Passed Introduced February 20, 2025

What this record is

Held by
August Winter & Sons, Inc 15 records across this site
Amount
$4.45M
Runs until
Not stated in the agenda text — the term is normally in the signed agreement, attached to the original item ↗
Type
award
Field
Utilities & energy
Compared to
$258K – $864K the middle half of 14 other August Winter & Sons, Inc contracts; median $476K — this one sits well outside that, which a longer term or wider scope will do, but is worth reading

utilities & energy contracts in WI that end within a year →
Governments publish the end date in the award. That date is when the work goes back out to bid, and it is usually stated years ahead.

Read automatically from the title of the official record. The source document below is authoritative.

August Winter & Sons, Inc also holds

To approve request by the Department of Public Works to award contract GBMFD 1-26 STATION 7 HVAC REPLACEMENT to August Winter & Sons, Inc. in the amou… $384K Green Bay, WI Consideration with possible action on request by the Department of Public Works to award contract GBMFD 1-26 STATION 7 HVAC REPLACEMENT to August Wint… $384K Green Bay, WI Discussion and possible action to award the contract for the Jacob's Ridge Lift Station Project to August Winter & Sons, Inc. in the amount of $1,297,… $1.30M New Berlin, WI Change orders #5 through #8 to August Winter & Sons, Inc. contract as part of the Appleton Wastewater Treatment Plant 2025 LBuilding HVAC and Receivin… $386K Appleton, WI Report of Bids and Resolution awarding contract to August Winter & Sons, Inc in the amount of $2,172,389.00 for the Hagar St Lift Station Improvements… $2.17M La Crosse, WI

All 15 records for August Winter & Sons, Inc →

Committee
Finance Committee
Introduced
February 20, 2025
On agenda
February 24, 2025
Passed
March 5, 2025

Where it was heard

Common Council Mar 5, 2025 approved Pass Finance Committee Feb 24, 2025 recommended for approval Pass

Watch what Appleton buys

This is one award. Appleton signs them continuously, and each one names a company and a date it runs out. Say what you sell and we will email you when the next one matches.

Free for 14 days, no card — and nothing charges itself: at day 14 the emails simply stop unless you choose to subscribe ($19 a month). One email when something matches, and nothing else. Unsubscribe from any of them. Searching stays free — it is public record.

↑ Back to top