24-0959
Request to approve Change Order No. 2 to contract 21-24 for H-23 Lightning Drive Extension Phase 1 for added drain tile and earthwork, in the amount of $72,830.00 resulting in a decrease in contingency from $92,934.82 to $20,104.82. Overall contract increases from $1,622,361.12 to $1,695,191.12.
What this record is
- Amount
- $73K
- Runs until
- no end date published in this record
- Type
- amendment
Read automatically from the title of the official record. The source document below is authoritative.
- Committee
- Finance Committee
- Introduced
- July 18, 2024
- On agenda
- July 22, 2024
- Passed
- August 7, 2024