26-1150A
Authorize Supplemental Agreement No. 1 to the engineering services contract with Garver, LLC, to amend the scope of work to include construction administration services to the Taxiway Apron Paved Islands Phase I at Dallas Executive Airport - Not to exceed $129,200.00, from $223,950.00 to $353,150.00 - Financing: Aviation Construction Fund *In alignment with Capital Improvement Program.
What this record is
- Held by
- Garver, LLC 61 records across this site
- Amount
- $129K
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
Garver, LLC also holds
Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute an Amendment to the Contract with Garver, LLC for Architecture/Engineerin… Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract with Garver, LLC, for Design and Related Professional Services… Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute a Contract with Garver, LLC for Professional Engineering Design Services … Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute an Additional Services Agreement with Garver, LLC for On-Call Services at… Consider/Discuss/Act on a Resolution Authorizing the City Manager to Execute an Agreement with Garver, LLC for Construction Phase Services for the McK…All 61 records for Garver, LLC →
- Committee
- Department of Aviation
- Requested by
- Department of Aviation (AVI)
- Introduced
- March 24, 2026
- On agenda
- May 13, 2026
- Enactment no.
- 26-0800; APPROVED