16-0660
Consideration of Change Order No. 1 (COF 2015-0062) with Judy Construction for the Water Treatment Plant Modifications Project (07/28/16 CIC 4-0).
What this record is
- Held by
- Judy Construction 6 records across this site
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
Judy Construction also holds
A Resolution accepting the bid of Judy Construction Co., in the amount of $2,945,000 for the East Hickman Pump Station Phase 2, for the Div. of Water … Consideration of Final Change Order to the Construction Contract (COF Contract No. 2015-0062) for the Water Treatment Plant Modifications Project with… Consideration of Change Order No. 3 to the Construction Contract (COF Contract No. 2015-0062) with Judy Construction Company for the Water Treatment P… Consideration of Change Order No. 2 to the Construction Contract (COF Contract No. 2015-0062) with Judy Construction for the Water Treatment Plant Mod… Consideration of Change Order No. 1 (COF 2015-0062) with Judy Construction for the Water Treatment Plant Modifications Project.- Committee
- Board of Mayor & Aldermen
- Requested by
- Engineering
- Introduced
- July 28, 2016
- On agenda
- August 9, 2016
- Passed
- August 9, 2016