Large Diameter Combined Sewer Rehabilitation Project, Change Order No. 5 Reflecting a decrease to the contract with Vortex Lining Systems in the amount of -$321,480.54. The pay items in Change Order No. 5 are primarily related to items that would address potential underground conditions or quantities that were included as contingency items. (DISTRICTS #1 & #5)

Resolution Passed Introduced August 29, 2025

What this record is

Held by
Vortex Lining Systems 8 records across this site
Amount
$321K
Runs until
no end date published in this record
Type
amendment
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Vortex Lining Systems also holds

Large Diameter Combined Sewer Rehabilitation Project Final Balancing Change Order No. 6 Reflecting a decrease to the contract with Vortex Lining Syste… Lombard, IL RECOMMENDATION from Director Houston Public Works that Houston City Council accept the work and authorize final payment, if any, of the contract with … Houston, TX Large Diameter Combined Sewer Rehabilitation Project, Change Order No. 4 Reflecting an increase of $7,586.33 to the contract with Vortex Lining System… $8K Lombard, IL Large Diameter Combined Sewer Rehabilitation Project, Change Order No. 3 Reflecting a decrease to the contract with Vortex Lining Systems in the amoun… $87K Lombard, IL Large Diameter Combined Sewer Rehabilitation Project, Change Order No. 2 Reflecting an increase to the contract with Vortex Lining Systems in the amou… $20K Lombard, IL

All 8 records for Vortex Lining Systems →

Committee
Village Board of Trustees
Requested by
Public Works Department
Introduced
August 29, 2025
Passed
September 18, 2025
Enacted
September 18, 2025
Enactment no.
R 48-25

Where it was heard

Village Board of Trustees Sep 18, 2025 adopted Pass Public Works & Environmental Concerns Sep 9, 2025 recommended to the Board of Trustees for approval Pass