40398
Large Diameter Combined Sewer Rehabilitation Project, Change Order No. 3 Reflecting a decrease to the contract with Vortex Lining Systems in the amount of $87,280.31. The line items address pay items that differ from the original bid quantities either being under or over the anticipated amounts. (DISTRICTS #1 & #5)
What this record is
- Held by
- Vortex Lining Systems 8 records across this site
- Amount
- $87K
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
Vortex Lining Systems also holds
Large Diameter Combined Sewer Rehabilitation Project Final Balancing Change Order No. 6 Reflecting a decrease to the contract with Vortex Lining Syste… RECOMMENDATION from Director Houston Public Works that Houston City Council accept the work and authorize final payment, if any, of the contract with … Large Diameter Combined Sewer Rehabilitation Project, Change Order No. 5 Reflecting a decrease to the contract with Vortex Lining Systems in the amoun… Large Diameter Combined Sewer Rehabilitation Project, Change Order No. 4 Reflecting an increase of $7,586.33 to the contract with Vortex Lining System… Large Diameter Combined Sewer Rehabilitation Project, Change Order No. 2 Reflecting an increase to the contract with Vortex Lining Systems in the amou…All 8 records for Vortex Lining Systems →
- Committee
- Village Board of Trustees
- Requested by
- Public Works Department
- Introduced
- December 3, 2024
- Passed
- December 19, 2024
- Enacted
- December 19, 2024
- Enactment no.
- R 67-24