FM-P-0036-26
Recommendation for the approval of a contract to Excel Electric, Inc., to replace the switchgear and generator at the Power Plant, for Facilities Management, for the period of October 13, 2026 through November 30, 2029, for a total contract amount not to exceed $5,865,000; per bid #26-069-FM.
What this record is
- Held by
- Excel Electric, Inc 4 records across this site
- Amount
- $5.87M
- Runs until
- November 30, 2029 3 years away date quoted from the award document
- Type
- contract
- Field
- Utilities & energy
- Compared to
- $95K – $479K the middle half of 4 other Excel Electric, Inc contracts; median $479K — this one sits well outside that, which a longer term or wider scope will do, but is worth reading
utilities & energy contracts in IL that end within a year →
Governments publish the end date in the award. That date is when the
work goes back out to bid, and it is usually stated years ahead.
Read automatically from the title of the official record. The source document below is authoritative.
Excel Electric, Inc also holds
FM – Excel Electric, Inc., 7140-0001 SERV - This contract is decreasing in the amount of $12,333.00 and closing due to the contract expiring. Recommendation for the approval of a contract purchase order to Excel Electric, Inc., to provide Civil and Electrical work for Generator Installation … Recommendation for the approval of a contract to Excel Electric, Inc., to install a medium voltage B-Feeder extension on the West campus, for Faciliti…- Committee
- Public Works Committee
- Requested by
- Facilities Management
- Introduced
- September 10, 2026
- On agenda
- October 6, 2026
Where it was heard
DuPage County Board Finance Committee Public Works CommitteeWatch what DuPage County buys
This is one award. DuPage County signs them continuously, and each one names a company and a date it runs out. Say what you sell and we will email you when the next one matches.
Free. One email when something matches, and nothing else. Unsubscribe from any of them.