Recommendation for the approval of a contract with Thomas Engineering Group, LLC, for Professional Construction Engineering Services for improvements along CH 23/Naperville Road, from Ridgeland Avenue to Diehl Road, Section 16-00195-06-CH, for the period of January 13, 2026, through May 31, 2028, for a contract total not to exceed $770,583. Professional Services (Architects, Engineers and Land Surveyors) vetted through a qualification- based selection process in compliance with the Local Government Professional Services Selection Act, 50 ILCS 510/0.01 et seq.

Transportation Requisition $30,000.01+ Adopted Introduced December 16, 2025

What this record is

Held by
Thomas Engineering Group, LLC 10 records across this site
Amount
$771K
Runs until
May 31, 2028 2 years away date quoted from the award document
Type
contract
Field
Professional services

See everything else expiring in this field →

Read automatically from the title of the official record. The source document below is authoritative.

Thomas Engineering Group, LLC also holds

North Grace Street Roadway Improvements - Resident Engineering Services Approving a contract with Thomas Engineering Group LLC in an amount not to exc… $303K Lombard, IL Approval of Private Engineering Services Consultant Agreement - Thomas Engineering Group Staff requests the approval of the contract with Thomas Engin… $40K Lombard, IL Approve the award of RFP 25-081, White Oak Roadway and Utility Improvements Preliminary and Design Engineering Services, to Thomas Engineering Group, … $209K Naperville, IL Downtown Sidewalk Project - Resident Engineering Contract Amendment No. 2 Approving a contract amendment with Thomas Engineering Group in the amount o… $17K Lombard, IL Highland Avenue Sewer Separation Project Resident Engineering Services Approving a contract with Thomas Engineering Group in an amount not to exceed $… $159K Lombard, IL

All 10 records for Thomas Engineering Group, LLC →

Committee
Transportation Committee
Requested by
Transportation
Introduced
December 16, 2025
On agenda
January 6, 2026
Passed
January 13, 2026

Where it was heard

Finance Committee Jan 13, 2026 Approved Pass DuPage County Board Jan 13, 2026 Approved Pass Transportation Committee Jan 6, 2026 Approved and Sent to Finance Pass