docketcity.com
24-2135

DT-P-0103A-23 Amendment to DT-P-0103-23, issued to Christopher B. Burke Engineering, Ltd., for Professional Preliminary Engineering Services along the East Branch DuPage River Trail, from Butterfield Road to the Illinois Prairie Path, to increase the funding in the amount of $126,429, resulting in an amended contract total amount of $1,626,429, an increase of 8.43%.

Transportation Change Order with Resolution Adopted Introduced August 6, 2024

What this record is

Held by
Burke Engineering, Ltd 20 records across this site
Amount
$126K
Runs until
no end date published in this record
Type
amendment
Field
Professional services

Read automatically from the title of the official record. The source document below is authoritative.

Burke Engineering, Ltd also holds

Recommendation for the approval of a contract to Christopher B. Burke Engineering, Ltd., for Professional Phase I Engineering Services for improvement… $268K DuPage County, IL Joint resolution appropriating a supplemental amount of $1,450,000 of Motor Fuel Tax funds and approving Change Order Number Three in the amount of $1… $1.21M Lake County, IL Joint resolution authorizing an agreement with Christopher B. Burke Engineering, Ltd., Rosemont, Illinois, for Phase III professional construction eng… $5.35M Lake County, IL Approval of Contract authorization with Christopher B. Burke Engineering Ltd. Rosemont, IL for General Engineering Services in the amount of $749,085.… $749K Lake County, IL DT-P-0103B-23 - Amendment to Resolution DT-P-0103A-23, issued to Christopher B. Burke Engineering, Ltd., for Professional Preliminary Engineering Serv… $795K DuPage County, IL

All 20 records for Burke Engineering, Ltd →

Committee
Transportation Committee
Requested by
Transportation
Introduced
August 6, 2024
On agenda
August 20, 2024
Passed
August 27, 2024

Where it was heard

Finance Committee Aug 27, 2024 Approved Pass DuPage County Board Aug 27, 2024 Approved Pass Transportation Committee Aug 20, 2024 Approved and Sent to Finance Fail