25-3429
*Approving a Change Order to Task Order No. 9 to Black & Veatch Corporation for construction phase services for replacement of activated sludge pumps, to include return activated sludge (RAS) and waste activated sludge (WAS) instrumentation and plumbing at the Richard A. Heyman Environmental Protection Facility in an amount not to exceed $37,295.00; Authorizing any necessary budget adjustments; Authorizing the City Manager to execute documents upon consent of the City Attorney.
What this record is
- Held by
- Black & Veatch Corporation 41 records across this site
- Amount
- $37K
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
Black & Veatch Corporation also holds
To authorize the Director of the Department of Public Utilities to modify and increase the contract with Black & Veatch Corporation for the Lower Olen… Actions pertaining to the Dewatering Cake Pump Improvement Project (Bid File No. 12600757): (Council District 3) 1. Adopt a finding of Categorical Exe… *Approving the additional effort proposal from Black & Veatch for Comprehensive Engineering Services during construction of the Richard A. Heyman Envi… [O-581-25] Authorizing the Mayor to execute a fifth amendment to the professional engineering services contract with Black & Veatch Corporation to ext… Black & Veatch Corporation - PO 7289-0001-SERV - Change Order to extend the contract from November 30, 2025 to November 30, 2026, no change to contrac…All 41 records for Black & Veatch Corporation →
- Committee
- City Commission
- Requested by
- Utilities
- Introduced
- February 18, 2025
- On agenda
- March 4, 2025
- Passed
- March 4, 2025
- Enacted
- March 4, 2025
- Enactment no.
- Res 25-040