docketcity.com

Finance Committee

January 6, 2025 ·5:30 PM Final

Council Chambers, 6th Floor

Agenda — 20 items

  1. 1. Call meeting to order
  2. 2. Pledge of Allegiance
  3. 3. Roll call of membership
  4. 4. Approval of minutes from previous meeting
  5. 5 12/09/24 Finance Committee Meeting minutes 24-1622 approved Pass
  6. 5. Public Hearing/Appearances
  7. 7 Ms. Diane Keuther, Commodore of the Appleton Yacht Club to present the Club's financial reports. 24-1625 presented
  8. 6. Action Items
  9. 9 Request to approve Contract Amendment #1 with Restoration Systems Inc. for Green Ramp Barrier Panel Emergency Repairs Phase 1, in an increase of $17,225, for a new not-to-exceed contract total of $64,455. 24-1623 recommended for approval Pass
  10. 10 Request to award the 2025 Interior Finishes and Furniture Project - Community Development to Chet Wesenberg Architect, LLC. for a sole-source contract not-to-exceed $67,400. 24-1624 recommended for approval Pass
  11. 7. Information Items
  12. 12 Contract 53-24 was awarded to Crafts, Inc. for $1,107,734 with a contingency of $66,464 for WWTP A, S, & V Roof Repair and Replacement. Change orders were approved totaling $4,800. Final contract amount is $1,112,534 with a contingency of $61,664. Payments issued to date total $1,078,227.30. Request final payment of $34,306.70. 24-1626 received and filed
  13. 13 Contract 84-22 was awarded to Miron Construction for $5,330,989 with a contingency of $799,648 for Sludge Storage Addition. Change orders were approved totaling $280,400.48. Final contract amount is $5,611,389.48 with a contingency of $519,247.52. Payments issued to date total $5,601,389.48. Request final payment of $10,000. 24-1627 received and filed
  14. 14 Contract 27-24 was awarded to Kruczek Construction Inc. for $2,959,994.96 with a contingency of $30,000 for W-24 Sewer & Water Reconstruction No. 1. Payments issued to date total $2,627,401.62. Request final payment of $184,731.70. 24-1628 received and filed
  15. 15 Contract 116-23 was awarded to Vinton Construction Company for the 2023 Lundgaard Park Phase One Construction Project in the amount of $911,177.70 with a contingency of $137,000. Change orders were issued totaling $14,200.54. Payments to date total $870,124.10. Request final payment of $55,254.14. 24-1629 received and filed
  16. 16 Contract 108-23 was awarded to Southport Engineered Systems, LLC. for the 2023 MSB CEA Shop HVAC Replacement Project in the amount of $664,550 with an 8% contingency of $53,164. Two change orders were issued in the amount of $35,337. Payments to date total $682,389.81. Request final payment of $17,497.19. 24-1630 received and filed
  17. 17 Contract 55-24 was awarded to Van Rite Plumbing Inc. for $524,896.87 for Y-24 Lead/Galvanized Water Service Replacement. Payments issued to date total $463,762.13. Request final payment of $55,479.92. 24-1631 received and filed
  18. 18 Contract 30-24 was awarded to Advance Construction Inc for Z-24 Water Reconstruction in an amount not to exceed $980,663. Payments issued to date total $404,554.52. Request final payment of $474,764.73. 24-1632 received and filed
  19. 19 The following 2024 Budget adjustments were approved by the Finance Director in accordance with Policy: General Fund - Library Community Partner - Other Reimbursements +$2,000 Community Partner - Supplies +$2,000 To record Wild Women in the Kitchen Grant General Fund - Library Materials Management - Other Reimbursements +$25 Materials Management - Books and Library Materials +$25 To record David Greene Memorial (Opening Day) General Fund - Library Childrens - Other Reimbursement +$100 Childrens - Office Supplies +$100 To record ESL Donation 24-1633 received and filed
  20. 8. Adjournment adjourned Pass

Watch Appleton

This is one agenda. Appleton publishes another every few weeks, and the thing you care about is rarely on the one you happened to find. Name it and we will email you when it appears.

Free for 14 days, no card — and nothing charges itself: at day 14 the emails simply stop unless you choose to subscribe ($19 a month). One email when something matches, and nothing else. Unsubscribe from any of them. Searching stays free — it is public record.

↑ Back to top