Contract 53-24 was awarded to Crafts, Inc. for $1,107,734 with a contingency of $66,464 for WWTP A, S, & V Roof Repair and Replacement. Change orders were approved totaling $4,800. Final contract amount is $1,112,534 with a contingency of $61,664. Payments issued to date total $1,078,227.30. Request final payment of $34,306.70.

Presentation Filed Introduced January 2, 2025

What this record is

Held by
Crafts, Inc 3 records across this site
Amount
$1.11M
Runs until
Not stated in the agenda text — the term is normally in the signed agreement, attached to the original item ↗
Type
award
Field
Construction

construction contracts in WI that end within a year →
Governments publish the end date in the award. That date is when the work goes back out to bid, and it is usually stated years ahead.

Read automatically from the title of the official record. The source document below is authoritative.

Crafts, Inc also holds

Request to award the Appleton Wastewater Treatment Plant M-K Tunnel Roofing Project contract to Crafts Inc. in the amount of $137,665 with a contingen… $151K Appleton, WI Request to award the 2024 AWWTP Roof Replacement Project contract to Crafts, Inc. in the amount of $1,107,734 with a 6% contingency of $66,464 for a p… $1.17M Appleton, WI
Committee
Finance Committee
Introduced
January 2, 2025
On agenda
January 6, 2025
Passed
January 6, 2025

Where it was heard

Finance Committee Jan 6, 2025 received and filed

Watch what Appleton buys

This is one award. Appleton signs them continuously, and each one names a company and a date it runs out. Say what you sell and we will email you when the next one matches.