Contract 55-25 was awarded to Scott Lamers Construction LLC for $486,212.08 for Y-25 Lead/Galvanized Water Service Replacement. Payments issued to date total $236,170.61. Request final payment of $179,296.68.

Report Action Item Action Item Introduced December 31, 2025

What this record is

Held by
Scott Lamers Construction LLC 3 records across this site
Amount
$486K
Runs until
no end date published in this record
Type
award
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Scott Lamers Construction LLC also holds

Request to award Unit Y-25 Lead/Galvanized Water Service Replacement to Scott Lamers Construction LLC in an amount not to exceed $486,212.08. $486K Appleton, WI Contract 35-23 was awarded to Scott Lamers Construction LLC for $400,910 with a contingency of $99,090 for Y-23 Lead/Galvanized Water Service Replacem… $475K Appleton, WI
Committee
Finance Committee
Introduced
December 31, 2025
On agenda
January 12, 2026
Passed
January 12, 2026

Where it was heard

Finance Committee Jan 12, 2026 presented