Request to award AWWTP Column and Plank Storage Upgrades Bid to Staab Construction in the amount of $353,000 with 2.5% contingency of $8,825 for a project total not to exceed $361,825.

Report Action Item Passed Introduced February 20, 2025

What this record is

Amount
$362K
Runs until
no end date published in this record
Type
award
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Committee
Finance Committee
Introduced
February 20, 2025
On agenda
February 24, 2025
Passed
March 5, 2025