Request to award AWWTP Column and Plank Storage Upgrades Bid to Staab Construction in the amount of $353,000 with 2.5% contingency of $8,825 for a project total not to exceed $361,825.

Report Action Item Passed Introduced February 20, 2025

What this record is

Amount
$362K
Runs until
Not stated in the agenda text — the term is normally in the signed agreement, attached to the original item ↗
Type
award
Field
Construction

construction contracts in WI that end within a year →
Governments publish the end date in the award. That date is when the work goes back out to bid, and it is usually stated years ahead.

Read automatically from the title of the official record. The source document below is authoritative.

Committee
Finance Committee
Introduced
February 20, 2025
On agenda
February 24, 2025
Passed
March 5, 2025

Where it was heard

Common Council Mar 5, 2025 approved Pass Finance Committee Feb 24, 2025 recommended for approval Pass

Watch what Appleton buys

This is one award. Appleton signs them continuously, and each one names a company and a date it runs out. Say what you sell and we will email you when the next one matches.

Free for 14 days, no card — and nothing charges itself: at day 14 the emails simply stop unless you choose to subscribe ($19 a month). One email when something matches, and nothing else. Unsubscribe from any of them. Searching stays free — it is public record.

↑ Back to top