Request to approve Change Order No. 1 to contract 42-24 for B-24 Asphalt Paving for additional sidewalk replacement, in the amount of $69,212.25 resulting in a decrease in contingency from $50,000 to $0. Overall contract increases from $1,407,816.40 to $1,477,028.65.

Report Action Item Passed Introduced November 7, 2024

What this record is

Amount
$69K
Runs until
no end date published in this record
Type
amendment
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Committee
Finance Committee
Introduced
November 7, 2024
On agenda
November 11, 2024
Passed
November 20, 2024

Where it was heard