24-1159

Request to approve sole source Engineering Services Contract to McMahon as part of Water Tower Booster Pump Improvements in the amount of $44,500 with a 10% contingency of $4,400 for a total not to exceed $48,900.

Report Action Item Passed Introduced August 23, 2024

What this record is

Amount
$49K
Runs until
no end date published in this record
Type
contract
Field
Professional services

Read automatically from the title of the official record. The source document below is authoritative.

Committee
Finance Committee
Introduced
August 23, 2024
On agenda
August 26, 2024
Passed
September 4, 2024

Where it was heard

Common Council Sep 4, 2024 approved Pass Finance Committee Aug 26, 2024 recommended for approval Pass