Request to award the AWWTP Waste Heat-to-Power Generator Install Project contract to Rhode Bros, Inc. in the amount of $563,500 with a 7.5% contingency of $42,263 for a project total not to exceed $605,763 along with the following budget amendment (2/3 vote of Council required). AWWTP Sludge Storage Building Addition Project -$200,000 AWWTP Waste Heat-to-Power Project +$200,000

Report Action Item Passed Introduced August 22, 2024
Committee
Finance Committee
Introduced
August 22, 2024
On agenda
August 26, 2024
Passed
September 4, 2024

Where it was heard

Common Council Sep 4, 2024 approved Pass Finance Committee Aug 26, 2024 recommended for approval Pass