Request to approve Contract Amendment and Change Order No. 1 to contract 21-24 for H-23 Lightning Drive Extension Phase 1 for excavation below subgrade and extra stone base, in the amount of $77,508.00 resulting in a decrease in contingency from $116,000.00 to $92,934.82. Overall contract increases from $1,544,853.12 to $1,622,361.12.

Report Action Item Passed Introduced May 16, 2024

What this record is

Amount
$78K
Runs until
no end date published in this record
Type
amendment
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Committee
Finance Committee
Introduced
May 16, 2024
On agenda
May 20, 2024
Passed
June 5, 2024

Where it was heard

Common Council Jun 5, 2024 approved Pass Finance Committee May 20, 2024 recommended for approval Pass