24-0033
Change Orders #9, #10, and #11 to Miron Construction contract as part of the AWWTP Sludge Storage Building Addition Construction Project totaling $19,646 resulting in a decrease in contingency from $552,192 to $532,546.
What this record is
- Amount
- $552K
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
- Committee
- Finance Committee
- Introduced
- January 4, 2024
- On agenda
- January 8, 2024
- Passed
- January 8, 2024