Contract 52-22 was awarded to Triple P Inc. dba Peters Concrete Company for the 2022 Ellen Kort Peace Park River Trail Project in the amount of $464,131.41 with a contingency of $46,413. Four change orders were approved totaling $45,146.69. Payments issued to date total $504,278.10. Request to issue the final payment of $5,000.00.

Presentation Filed Introduced January 3, 2024

What this record is

Held by
Triple P Inc 3 records across this site
Amount
$464K
Runs until
no end date published in this record
Type
award
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Triple P Inc also holds

Request to award Unit B-26 Asphalt Paving to Triple P Inc. dba Peters Concrete Company in the amount of $1,244,583.86 with a 3.6% contingency of $45,0… $1.29M Appleton, WI Request to award Unit H-23 Lightning Drive Sewer & Water, Grade & Gravel, and Bridge Construction to Triple P Inc., dba Peters Concrete Company, in th… $1.66M Appleton, WI
Committee
Finance Committee
Introduced
January 3, 2024
On agenda
January 8, 2024
Passed
January 8, 2024

Where it was heard

Finance Committee Jan 8, 2024 received and filed