Contract 124-22 was awarded to Rohde Brothers for $223,900 with a contingency of $26,868 for WW F-1 Bldg HVAC. Change orders were approved totaling $5,447. Final contract amount is $229,347 with a contingency of $21,421. Payments issued to date total $198,222.50. Request final payment of $31,124.50.