24-0013
Request to approve Change Order #4 to contract 72-22 for Unit H-21 Redundant Raw Water Line to increase for unanticipated site conditions in the amount of $176,232.54 resulting in a decrease in contingency from $244,549.71 to $0.00. No change to overall contract amount.
What this record is
- Amount
- $176K
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
- Committee
- Finance Committee
- Introduced
- January 3, 2024
- On agenda
- January 8, 2024
- Passed
- January 17, 2024