A resolution awarding a contract to R. L. Alia Company, in the amount of $1,667,959.00, plus a 20 percent contingency, for a projected contract total of $2,001,550.80, plus applicable taxes, budgeted from the Wastewater and Public Works Streets Initiative funds, for the replacement of wastewater sewer mains, roadways, and curb ramps on the North 10th and Stevens Street project - Specification No. ES24-0157F. [Kirk Myklestad, P.E., Professional Engineer; Geoffrey M. Smyth, P.E., Interim Director, Environmental Services]
What this record is
- Held by
- Alia Company 18 records across this site
- Amount
- $1.67M
- Runs until
- no end date published in this record
- Type
- award
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
Alia Company also holds
A resolution awarding a contract to R.L. Alia Company, in the amount of $1,463,284.00, plus a 10 percent contingency, budgeted from the Transportation… A resolution awarding a contract to R.L. Alia Company, in the amount of $4,107,365.00, plus a 15 percent contingency, budgeted from various funds, for… A resolution awarding a contract to R.L. Alia Company, in the amount of $6,163,769.00, plus a 10 percent contingency, budgeted from the Transportation… A resolution awarding a contract to R.L. Alia Company, in the amount of $6,748,119.00, plus a 10 percent contingency, budgeted from the Paths and Trai… A resolution awarding a contract to R.L. Alia Company, in the amount of $6,689,184.65, plus applicable taxes, plus a 15 percent contingency, for a cum…All 18 records for Alia Company →
- Committee
- City Council
- Requested by
- Purchasing
- Introduced
- January 16, 2025
- On agenda
- January 28, 2025
- Passed
- January 28, 2025