North Shore Sewer Transmission System Construction Update Details: The North Shore Sewer Transmission System construction is six months into the yearlong project. Staff provided an update to City Council about construction progress, schedule and elements of the project to be completed in the final six months. Presenter: Sam Adams, Utilities Manager