REP 17-037
North Shore Sewer and Water Transmission System Project Update (5:45 p.m.) Details: City staff, with support from the OTAK and CH2M consultant teams, are nearing design completion on the North Shore Sewer Transmission System Project and anticipate advertising for bids in February 2017. The project includes three sewer pump stations, approximately 4.5 miles of sewer transmission piping and will include a new pedestrian bridge over the Lacamas Lake/Round Lake Channel. In partnership with the Camas School District, the project will also include approximately 2.3 miles of water transmission main to serve the new Lacamas Heights Elementary School. Staff will provide a brief update on the project, primarily focusing on the construction sequencing and impacts to traffic throughout the duration of the year-long project. Presenter: Steve Wall, Public Works Director
- Committee
- CITY COUNCIL WORKSHOP
- Requested by
- Public Works
- Introduced
- January 24, 2017
- On agenda
- January 27, 2017