docketcity.com
REP 16-085

STEP Sewer Transmission Main Project Change Order Details: Change Order No. 3 for the STEP Sewer Transmission Main project is for several required items including fabrication of parts to match existing piping and cleanup related to a water main break and replacement of the deteriorated water main. A full description of the nine items included with this change order are included in the attached Change Order No. 3. The total for this change order is $132,995.40 and is funded by a Public Works Trust Fund (PWTF) loan and by the Water Utility Fund. This project is now substantially complete. Change Order No. 3 is for 5.2% of the original contract bid. The total amount of all change orders is 7.5% of the original contact bid. Presenter: James Carothers, Engineering Manager

Informational Report Meeting Item Introduced March 1, 2016

What this record is

Amount
$133K
Runs until
Not stated in the agenda text — the term is normally in the signed agreement, attached to the original item ↗
Type
amendment
Field
Construction

construction contracts in WA that end within a year →
Governments publish the end date in the award. That date is when the work goes back out to bid, and it is usually stated years ahead.

Read automatically from the title of the official record. The source document below is authoritative.

Committee
CITY COUNCIL WORKSHOP
Requested by
Public Works
Introduced
March 1, 2016
On agenda
March 7, 2016

Watch what Camas buys

This is one award. Camas signs them continuously, and each one names a company and a date it runs out. Say what you sell and we will email you when the next one matches.

Free for 14 days, no card — and nothing charges itself: at day 14 the emails simply stop unless you choose to subscribe ($19 a month). One email when something matches, and nothing else. Unsubscribe from any of them. Searching stays free — it is public record.

↑ Back to top