STEP Sewer Transmission Main Project Change Order Details: Change Order No. 3 for the STEP Sewer Transmission Main project is for several required items including fabrication of parts to match existing piping and cleanup related to a water main break and replacement of the deteriorated water main. A full description of the nine items included with this change order are included in the attached Change Order No. 3. The total for this change order is $132,995.40 and is funded by a Public Works Trust Fund (PWTF) loan and by the Water Utility Fund. This project is now substantially complete. Change Order No. 3 is for 5.2% of the original contract bid. The total amount of all change orders is 7.5% of the original contact bid. Presenter: James Carothers, Engineering Manager
What this record is
- Amount
- $133K
- Runs until
- Not stated in the agenda text — the term is normally in the signed agreement, attached to the original item ↗
- Type
- amendment
- Field
- Construction
construction contracts in WA that end within a year →
Governments publish the end date in the award. That date is when the
work goes back out to bid, and it is usually stated years ahead.
Read automatically from the title of the official record. The source document below is authoritative.
- Committee
- CITY COUNCIL WORKSHOP
- Requested by
- Public Works
- Introduced
- March 1, 2016
- On agenda
- March 7, 2016