Slow Sand Water Treatment Plant Change Order Details: Change Order No. 2 for the water treatment plant project is for several miscellaneous items including a septic tank design and installation of additional parking lot drainage. The cost of this change order is $66,660.07 and is funded by a Washington State Department of Health (WSDOH) Drinking Water State Revolving Fund (SRF) loan and is included in the 2016 Budget. This change order increases the project cost by 1.13%. The total of all change orders to date is 1.83% of the original contract bid. Presenter: James Carothers, Engineering Manager
What this record is
- Amount
- $67K
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
- Committee
- CITY COUNCIL WORKSHOP
- Requested by
- Public Works
- Introduced
- March 1, 2016
- On agenda
- March 7, 2016