REP 16-058

Wastewater Treatment Plant Spill Control Plan Consultant Contract Details: As a requirement of the City's Wastewater Treatment Plant's National Pollutant Discharge Elimination System (NPDES) Waste Discharge Permit, the City must prepare a Spill Control Plan (Plan) for the facility. The Plan must address prevention, containment and spill response. Gray and Osborne, Inc. has submitted a scope of work to complete the Plan for an amount not-to-exceed $5,200. Sewer funds are available to complete this project. Presenter: Sam Adams, Utilities Manager

Informational Report Meeting Item Introduced February 10, 2016

What this record is

Held by
Gray and Osborne, Inc 9 records across this site
Amount
$5K
Runs until
no end date published in this record
Type
contract
Field
Utilities & energy

Read automatically from the title of the official record. The source document below is authoritative.

Gray and Osborne, Inc also holds

$579,838 Gray and Osborne, Inc. 544' Zone Reservoir Project Professional Services Agreement (Submitted by Sam Adams) Camas, WA Gray and Osborne, Inc. Infiltration and Inflow Study Professional Services Agreement Presenter: Sam Adams, Utilities Manager Camas, WA $152,600 to Gray and Osborne, Inc. for Wastewater Treatment Plant and Parker's Landing Preliminary Well Design Professional Services Agreement (Submit… Camas, WA Consultant Services Contract - Parker's Landing and Wastewater Treatment Plant (WWTP) Test Well Development Details: The City has solicited consultant… $153K Camas, WA Consultant Services for Phase I/II Environmental Site Assessment for Potential Reservoir Site Details: Staff has been working on siting a new 544-Foot… $27K Camas, WA

All 9 records for Gray and Osborne, Inc →

Committee
CITY COUNCIL WORKSHOP
Requested by
Public Works
Introduced
February 10, 2016
On agenda
February 16, 2016