REP 15-587
STEP Sewer Transmission Main Change Order Details: This change order includes additional work for removal and disposal of boulders and buried concrete pavement, extra depth sawcutting where the pavement depth was greater than anticipated, additional sawcutting for a required route change, and other various minor repairs and necessary appurtenance installations. The contractor is also being paid for standby time due to archaeological finds. The total amount of this change order is $47,975.48 including tax. This project, including this change order, is funded by a Public Works Trust Fund loan. Presenter: James Carothers, Engineering Manager
What this record is
- Amount
- $48K
- Runs until
- Not stated in the agenda text — the term is normally in the signed agreement, attached to the original item ↗
- Type
- amendment
- Field
- Construction
construction contracts in WA that end within a year →
Governments publish the end date in the award. That date is when the
work goes back out to bid, and it is usually stated years ahead.
Read automatically from the title of the official record. The source document below is authoritative.
- Committee
- CITY COUNCIL WORKSHOP
- Requested by
- Public Works
- Introduced
- December 1, 2015
- On agenda
- December 7, 2015
Watch what Camas buys
This is one award. Camas signs them continuously, and each one names a company and a date it runs out. Say what you sell and we will email you when the next one matches.