Authorized Pay Estimate No. 2, Final, to Nutter Corporation for the NW 10th Avenue and Ivy Street & Drake Street Stormwater Facilities Rehabilitation Project in the amount of $15,686.61 and accept the project as complete. The total project cost, including design, permitting and construction will be approximately $150,000. The budgeted amount for the project is $250,000. (Submitted by James Carothers)

Action Item Consent Agenda Introduced November 14, 2017
Committee
CITY COUNCIL REGULAR
Requested by
Public Works
Introduced
November 14, 2017
On agenda
November 20, 2017