Consider a resolution authorizing the Mayor to execute Quantity Adjustment/Change Order No. 1 with Capital Excavation Company for the Gattis School Road Segment 6 Project.

Resolution Agenda Ready Introduced January 22, 2024

What this record is

Held by
Capital Excavation Company 8 records across this site
Runs until
no end date published in this record
Type
amendment
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Capital Excavation Company also holds

Consider a resolution authorizing the Mayor to execute Quantity Adjustment/Change Order No. 2 with Capital Excavation Company for the Wyoming Springs … Round Rock, TX Consider a resolution authorizing the Mayor to execute Quantity Adjustment/Change Order No. 1 with Capital Excavation Company for the Wyoming Springs … Round Rock, TX Discuss and consider approval of a joint-bid contract between the City of New Braunfels and New Braunfels Utilities, with Capital Excavation Company f… New Braunfels, TX Approving a construction contract with Capital Excavation Company, Inc. in the amount of $15,130,910 for construction services associated with the Pic… $15.1M Pflugerville, TX Approving a change order in the amount of $395,207 and 156 additional days for the construction contract for Kelly Lane Phase 2 roadway improvements p… $395K Pflugerville, TX

All 8 records for Capital Excavation Company →

Committee
City Council
Requested by
Transportation
Introduced
January 22, 2024
On agenda
February 8, 2024
Passed
February 8, 2024

Where it was heard

City Council Feb 8, 2024 approve Pass