26-4150
Request for approval of a change in contract with Spawglass Construction Corp. in connection with Challenger 7 Improvements, adding 215 calendar days, with an addition in the amount of $65,865.78, Job No. 24/0264-4, UPIN 20101MF1F101, Precinct 2, MWBE Contracted Goal: 41%, MWBE Current Participation: 42.85%.
What this record is
- Held by
- Spawglass Construction Corp 23 records across this site
- Amount
- $66K
- Runs until
- no end date published in this record
- Type
- contract
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
Spawglass Construction Corp also holds
Approval of Change Order #3 to CIP 26-565 Construction Manager at Risk for Building Maintenance for Brazos County Expo Complex with SpawGlass Construc… Request for approval of a change in contract with Spawglass Construction Corp. in connection with Connectivity Project - Deussen-Eisenhower - 2021, wi… Request for approval of a change in contract with Spawglass Construction Corp., in connection with Connectivity Project - Deussen-Eisenhower - 2021, w… Approval of Change Order #2 to CIP 25-565 Construction Manager at Risk for Building Maintenance for Brazos County Expo Center with SpawGlass Construct… Request for approval of a change in contract with Spawglass Construction Corp. in connection with Connectivity Project - Deussen-Eisenhower - 2021, wi…All 23 records for Spawglass Construction Corp →
- Committee
- Commissioners Court
- Requested by
- County Engineer
- Introduced
- June 23, 2026
- On agenda
- July 9, 2026
- Passed
- July 9, 2026