docketcity.com
25-4550

Request for approval of a change in contract with Spawglass Construction Corp., in connection with Challenger 7 Park - Boardwalk Renovation - 2020, with an addition in the amount of $30,174.75, Job No. 24/0264-1, UPIN 20101MF1F101, Precinct 2, MWBE Contracted Goal: 14.68%, MWBE Current Participation: 7.90%.

Contract - Amendment Passed Introduced July 21, 2025

What this record is

Held by
Spawglass Construction Corp 23 records across this site
Amount
$30K
Runs until
no end date published in this record
Type
contract
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Spawglass Construction Corp also holds

Approval of Change Order #3 to CIP 26-565 Construction Manager at Risk for Building Maintenance for Brazos County Expo Complex with SpawGlass Construc… Bryan, TX Request for approval of a change in contract with Spawglass Construction Corp. in connection with Connectivity Project - Deussen-Eisenhower - 2021, wi… $59K Harris County, TX Request for approval of a change in contract with Spawglass Construction Corp., in connection with Connectivity Project - Deussen-Eisenhower - 2021, w… $182K Harris County, TX Approval of Change Order #2 to CIP 25-565 Construction Manager at Risk for Building Maintenance for Brazos County Expo Center with SpawGlass Construct… Bryan, TX Request for approval of a change in contract with Spawglass Construction Corp. in connection with Connectivity Project - Deussen-Eisenhower - 2021, wi… $132K Harris County, TX

All 23 records for Spawglass Construction Corp →

Committee
Commissioners Court
Requested by
County Engineer
Introduced
July 21, 2025
On agenda
August 7, 2025
Passed
August 7, 2025

Where it was heard

Commissioners Court Aug 7, 2025 approved Pass