20-10441
Ordinance amending the FY 2020/2021 Capital Improvement Projects Budget; Construction contract with Gomez Brothers Construction, Inc. for Brent Court Storm Drainage Improvements in the total amount of $387,046.00; material testing with Team Consultants in the amount of $14,377.80; in-house engineering in the amount of $19,352.30; and 5% construction contract contingency in the amount of $19,352.30 for a total project cost of $440,128.40
What this record is
- Amount
- $387K
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
- Committee
- Engineering
- Introduced
- October 2, 2020
- On agenda
- October 13, 2020
- Passed
- October 13, 2020
- Enacted
- October 13, 2020
- Enactment no.
- ORD 10912-2020