Fire Station 4+6 Change Order/Amendment No. 3 with Key Construction in the amount of $144,319.71 for extended contractor General Conditions due to weather impacts, added interior door, catwalk structure, louver covers, sanitary sewer piping revisions, added power, low voltage controls, dimmer switches, exhaust fan relocation, electrical panel changes, removal of equipment bay drainage, ceiling fan supports, landscape revisions, tile changes, removal of additional trench drain, elimination of sand/oil separator, tree removal and final project buy-out/scope coordination
What this record is
- Held by
- Key Construction 5 records across this site
- Amount
- $144K
- Runs until
- no end date published in this record
- Type
- amendment
- Field
- Construction
Read automatically from the title of the official record. The source document below is authoritative.
Key Construction also holds
Fire Station 4+6 Final Change Order/Amendment No. 4 with Key Construction in the amount of $62,885.89 for Proposed Change Orders (PCOs) #005, #006 and… Change Order/Amendment No. 2 for Fire Station 6 with Key Construction in the amount of $105,183.26 for Fire Station 6 plumbing revisions, increased el… Change Order/Amendment No. 1 with Key Construction in the amount of $4,400,000 for the balance of construction cost for a new Fire Station 4 and addit… Construction Manager at Risk (CMAR) Contract with Key Construction for pre-construction services for a new Fire Station 4 and addition to Fire Station…- Committee
- Engineering
- Introduced
- April 25, 2019
- On agenda
- May 7, 2019
- Passed