Construction Manager at Risk (CMAR) Contract with Key Construction for pre-construction services for a new Fire Station 4 and addition to Fire Station 6 in the amount of $15,000 and approve a Construction Services Fee of 1.00% to be applied to the actual approved construction costs for the new Fire Station 4 and addition to Fire Station 6 work at a later time

Agenda Item Consent Agenda Introduced May 7, 2018

What this record is

Held by
Key Construction 5 records across this site
Amount
$15K
Runs until
no end date published in this record
Type
contract
Field
Construction

Read automatically from the title of the official record. The source document below is authoritative.

Key Construction also holds

Fire Station 4+6 Final Change Order/Amendment No. 4 with Key Construction in the amount of $62,885.89 for Proposed Change Orders (PCOs) #005, #006 and… $63K Grand Prairie, TX Fire Station 4+6 Change Order/Amendment No. 3 with Key Construction in the amount of $144,319.71 for extended contractor General Conditions due to wea… $144K Grand Prairie, TX Change Order/Amendment No. 2 for Fire Station 6 with Key Construction in the amount of $105,183.26 for Fire Station 6 plumbing revisions, increased el… $105K Grand Prairie, TX Change Order/Amendment No. 1 with Key Construction in the amount of $4,400,000 for the balance of construction cost for a new Fire Station 4 and addit… $4.40M Grand Prairie, TX
Committee
Engineering
Introduced
May 7, 2018
On agenda
June 5, 2018
Passed
June 5, 2018