20044-25a

Approval of Task Order No.5, AGR 22-18c for the Abiquiu Hydroelectric Plant Firewall and Office Project with GME General Building, LLC in the Amount of $409,207.95 plus Applicable Gross Receipts Tax

Briefing/Report (Dept,BCC) - Action Requested Consent Introduced April 3, 2025

What this record is

Held by
GME General Building, LLC
Amount
$409K
Runs until
no end date published in this record
Type
contract

Read automatically from the title of the official record. The source document below is authoritative.

Committee
Board of Public Utilities
Requested by
Department of Public Utilities
Introduced
April 3, 2025
On agenda
May 21, 2025
Passed
May 21, 2025

Where it was heard

Board of Public Utilities May 21, 2025 approval